Project Overview Sewer System Improvements
Project will consist of rehabilitating defects in the sanitary sewer collection system that are identified in the FY22 sanitary sewer evaluation survey (SSES) Project. Potential rehabilitation efforts will include cured-in-place pipe (CIPP) lining, manhole rehabilitation and miscellaneous point repairs. The project is part of the City of Auburn's <a href="">Other</a>.
Status
- Design
- Bid Advertisement
- Contracts
- Construction
80%
The contract was awarded to Vortex Services, LLC by Auburn City Council on July 16, 2024. The notice to proceed was issued effective October 15th, 2024. Contractor completed initial cleaning and pre-CCTV during Thanksgiving break. Contractor mobilized to begin CIPP work and manhole rehabilitation work the week of 12/16/2024. Lining of the sewer main beneath Jordan Hare Stadium is expected to begin 12/26/2024.
Photos




Timeline
Close Out Finishes
May 13, 2025
Close Out Starts
Apr 14, 2025
Construction Finishes
Apr 13, 2025
Construction Starts
Oct 15, 2024
Contracts Finishes
Aug 4, 2024
City Council / AWWB Starts
Jul 16, 2024
Contracts Starts
Jul 16, 2024
Bid Opening Starts
Jun 27, 2024
Bid Advertisement Finishes
Jun 27, 2024
Bid Advertisement Starts
Jun 1, 2024
Design Finishes
May 31, 2024
Design Starts
Oct 1, 2023